City, Developer Expected To Pay More For River Place

By Christina Haley O'Neal, posted Aug 4, 2017
A rendering of River Place in downtown Wilmington. (Courtesy of the city of Wilmington)
Cost estimates for the construction of River Place, a mixed-use project that is replacing the Water Street parking deck in downtown Wilmington, have increased by several million dollars since the original development agreement was approved in June 2016.

In the revised agreement, the city of Wilmington and East West Partners, the Chapel Hill-based firm developing the project, are splitting an additional cost of $7.6 million, according to a release from the city. The city’s additional cost would be $3.65 million and East West Partners cost would be $3.94 million.

“The design for River Place was started two years ago. During this time, construction costs have escalated significantly. East West Partners has absorbed these costs and made creative adjustments in its plans, in both design solutions and construction methods, to partially accommodate these increased costs without sacrificing the quality of River Place," Roger Perry, owner of East West Partners, explained in an email. "In spite of these creative solutions, our final budget has, nonetheless, increased during this period by over $5M. It is perfectly understandable that the same has happened to the city’s budget for the parking deck. This has been a very collaborative effort in creating a public-private partnership, and we are confident that as the city goes through this necessary process, it will see the value in making these budget adjustments so the project can proceed immediately."

Working with the general contractor Barnhill Construction on the project details, the city said revised cost estimates reflect construction price increases.

City spokeswoman Malissa Talbert attributed the cost increases to additional work on the site, finalizing design plans and an improving economy leading to higher costs since the price agreements were approved.

Cost of development was originally expected at about $75.6 million, but the new total in the development agreement that will be put to city council this month is around $83.2 million, according to numbers released by the development group.

Talbert said the city's previous cost was at $19.7 million, but the city’s estimated cost with the change is now at $23.4 million.

Designs for the 13-story River Place project include condominiums, apartments, restaurants, a fitness studio, other commercial tenants and a new parking deck.

Officials had previously said construction of River Place was scheduled to be complete by mid-2019. The project appeared to experience delays after a ceremonial groundbreaking event in May.

The price adjustment is one of the next steps the city is taking in its public-private partnership with East West Partners toward the upcoming demolition of the old Water Street Deck and construction at the site, city officials said in the release.

Perry said Friday that another major factor in the cost is the price of labor, which has "increased significantly" since discussions about the project began. 

As for the project timeline, Perry added, "These things are complicated and they take a long time, and I don’t think it’s been slow; I think it’s been at a normal pace."

He said the first phases in the project are still expected to be ready late in the first quarter or early in the second quarter of 2019.

Almost 50 percent of the retail space has been leased out and 70 percent of the condominiums have been sold, Perry said Friday.

“The market has been very receptive,” Perry said. “We are really excited about the building … and we’ve enjoyed working with the city on the project. It's energizing and exciting because it’s such an incredible project.”

The revised agreement will be up for a public hearing and approval by Wilmington City Council members at their Aug. 15 meeting. If the council approves the new agreement with the added cost of construction, demolition could begin in October, Talbert said.
Ico insights

INSIGHTS

SPONSORS' CONTENT
Susan 2 april242017

Divorced? You May Be Eligible for Boosted Retirement Benefits

Susan Willett - Old North State Trust, LLC
Mike stonestreet 300x300

Play it Safe When Planning Summer Celebrations

Mike Stonestreet - CAMS (Community Association Management Services)
Volety 0020 1121724229

New Interdisciplinary Studies Program Opens Doors for Former Seahawks

Aswani Volety - UNCW College of Arts and Sciences

Trending News

NHRMC Buys Wilmington Property From International Paper

Cece Nunn - Aug 15, 2018

Untappd Leads Pack Of Local Firms On Inc. 5000 List

Christina Haley O'Neal - Aug 15, 2018

Wilmington Brewing Co. Plans Expansion

Christina Haley O'Neal - Aug 16, 2018

Trampoline Park To Open Saturday At Mayfaire

Johanna Cano - Aug 16, 2018

Law Firm Moves To Murchison Building

Johanna Cano - Aug 15, 2018

In The Current Issue

Apiture Launches Banking Features

Two new banking tools introduced by Wilmington-based Apiture are designed to help banks give customers a better handle on their spending....


Low Impact Building With High Rewards

Pam Fasse, president and licensed general contractor for Fasse bldgs., says that she always gravitated toward project management and design...


Hitting The Right Note On Music Careers

For those in music, hitting the road full time can take a mix of talent and business know how....

Book On Business

The 2018 WilmingtonBiz: Book on Business is an annual publication showcasing the Wilmington region as a center of business.

Order Your Copy Today!


Galleries

Videos

2018 Power Breakfast - Dishing on the Restaurant Biz
2018 WilmingtonBiz Expo - Keynote Lunch with Eric Dinenberg, Rouse Properties
2017 Health Care Heroes