City, Developer Expected To Pay More For River Place

By Christina Haley O'Neal, posted Aug 4, 2017
A rendering of River Place in downtown Wilmington. (Courtesy of the city of Wilmington)
Cost estimates for the construction of River Place, a mixed-use project that is replacing the Water Street parking deck in downtown Wilmington, have increased by several million dollars since the original development agreement was approved in June 2016.

In the revised agreement, the city of Wilmington and East West Partners, the Chapel Hill-based firm developing the project, are splitting an additional cost of $7.6 million, according to a release from the city. The city’s additional cost would be $3.65 million and East West Partners cost would be $3.94 million.

“The design for River Place was started two years ago. During this time, construction costs have escalated significantly. East West Partners has absorbed these costs and made creative adjustments in its plans, in both design solutions and construction methods, to partially accommodate these increased costs without sacrificing the quality of River Place," Roger Perry, owner of East West Partners, explained in an email. "In spite of these creative solutions, our final budget has, nonetheless, increased during this period by over $5M. It is perfectly understandable that the same has happened to the city’s budget for the parking deck. This has been a very collaborative effort in creating a public-private partnership, and we are confident that as the city goes through this necessary process, it will see the value in making these budget adjustments so the project can proceed immediately."

Working with the general contractor Barnhill Construction on the project details, the city said revised cost estimates reflect construction price increases.

City spokeswoman Malissa Talbert attributed the cost increases to additional work on the site, finalizing design plans and an improving economy leading to higher costs since the price agreements were approved.

Cost of development was originally expected at about $75.6 million, but the new total in the development agreement that will be put to city council this month is around $83.2 million, according to numbers released by the development group.

Talbert said the city's previous cost was at $19.7 million, but the city’s estimated cost with the change is now at $23.4 million.

Designs for the 13-story River Place project include condominiums, apartments, restaurants, a fitness studio, other commercial tenants and a new parking deck.

Officials had previously said construction of River Place was scheduled to be complete by mid-2019. The project appeared to experience delays after a ceremonial groundbreaking event in May.

The price adjustment is one of the next steps the city is taking in its public-private partnership with East West Partners toward the upcoming demolition of the old Water Street Deck and construction at the site, city officials said in the release.

Perry said Friday that another major factor in the cost is the price of labor, which has "increased significantly" since discussions about the project began. 

As for the project timeline, Perry added, "These things are complicated and they take a long time, and I don’t think it’s been slow; I think it’s been at a normal pace."

He said the first phases in the project are still expected to be ready late in the first quarter or early in the second quarter of 2019.

Almost 50 percent of the retail space has been leased out and 70 percent of the condominiums have been sold, Perry said Friday.

“The market has been very receptive,” Perry said. “We are really excited about the building … and we’ve enjoyed working with the city on the project. It's energizing and exciting because it’s such an incredible project.”

The revised agreement will be up for a public hearing and approval by Wilmington City Council members at their Aug. 15 meeting. If the council approves the new agreement with the added cost of construction, demolition could begin in October, Talbert said.
Ico insights

INSIGHTS

SPONSORS' CONTENT
Mike stonestreet 300x300

Ditch the Jargon: Simple Tips for Effective Management

Mike Stonestreet - CAMS (Community Association Management Services)
Jeff metrocopy

Public Adjusters are Your Advocates After the Storm

Jeffrey Feldstein - Metro Public Adjustment
Fredheadshot 5119113348

5 Ways to Ensure Long-Lasting, Quality Window Treatments

Fred Kumpel - Strickland's Home

Trending News

Wheelz Pizza Aims To Revolutionize Pizza Delivery

Jessica Maurer - May 22, 2019

Cameron Apartment Project Rezoning Request To Come Before Planning Board

Jenny Callison - May 23, 2019

JuSea To Offer Healthy Options On Carolina Beach Boardwalk

Jessica Maurer - May 22, 2019

New Tenants Announced For Leland Retail Center

Cece Nunn - May 23, 2019

Home Sales In April Slumped 12% In Wilmington Area; Decline Blamed On Inventory

Cece Nunn - May 22, 2019

In The Current Issue

Info Junkie: Jim R. Roberts

Info Junkie Jim R. Roberts, Founder of Network for Entrepreneurs in Wilmington (NEW) and Wilmington Angels for Local Entrepreneurs (WALE), o...


Officials Forecast Hot Summer Travel Season

Marketing efforts by the Wilmington and Beaches Convention & Visitors Bureau (CVB), coupled with mended tourist attractions, are behind the...


Curiosity Sparks Engineer's Career

On a day in Wilmington about four decades ago, elementary school student Ron Sparks asked a pharmacist a question, then watched as the blood...

Book On Business

The 2019 WilmingtonBiz: Book on Business is an annual publication showcasing the Wilmington region as a center of business.

Order Your Copy Today!


Galleries

Videos

2019 WilmingtonBiz Expo Keynote Lunch - CEO, nCino, Pierre Naude`
Transporting the Future - Power Breakfast 3.12.2019
Health Care Heroes 2018