ILM Cuts Costs, Awards Contract In Final Phase Of Expansion

By Christina Haley O'Neal, posted Nov 15, 2019
Crews are shown working in September on phase two of Wilmington International Airport’s terminal expansion and renovation project. (Photo courtesy of ILM)

The Wilmington International Airport has reduced the scope of its airport expansion and renovation by $3 million in the last leg of the project to keep it within budget and award the final construction contract.

Monteith Construction Corp. in late August submitted a total bid for phase three work at over $52.1 million, which was higher than airport officials expected. To reduce costs, ILM shed a bid option to expand the airport's baggage claim area, valued at $5.4 million, and found $3 million in other cuts to bring the project's base bid to $43.7 million, said Granseur Dick, ILM's planning and development director.

Negotiated cuts included changing HVAC piping and electrical cabling materials and furniture cost reductions, Dick said. Airport officials also decided not to purchase one of three jet bridges planned within the contract.

The $43.7 million base bid, plus $2 million in additional funds for any unforeseen costs to the project, brought the total contract to nearly $46 million. That contract was delivered to Monteith Construction on Wednesday, Dick said.

Monteith Construction has now been awarded all three phases of the $60 million project. It completed the first round of the work in March and is currently constructing phase two.

The second portion of the project is about 40% complete and on schedule for completion in June, Dick said.

ILM has not set a date to begin construction on the final phase of work but anticipates the project will start soon after the new year, Dick said.

The final contract includes renovating the existing terminal and adds about 69,600 square feet of new space, according to the most recent figure. The work will build a new concourse, expand the TSA checkpoint area and add additional gates, as well as add more dining and retail space to the airport.

Dick said the airport has enough funding to begin the project with $14.4 million in secured funds, including $3.1 million from an FAA grant, $8.9 million in airport reserves and $2.4 million in passenger facility charges (PFC).

There is $33.6 million anticipated to come in through multi-year FAA Airport Improvement Program grants and seven years of future PFC revenue. The airport authority is also evaluating the potential use of a $20 million loan -- already approved by New Hanover County commissioners -- to bridge the gap between the construction project's cash flow needs and the future FAA grants, Dick said.

Airport officials also hope to receive grants through the N.C. Department of Transportation and from extra FAA discretionary grants, Dick said.

"Additional grants, if awarded, would free up reserves for the authority to perform other needed airfield and expansion/capacity-related projects or reduce the optional loan needs," he said.

Ico insights

INSIGHTS

SPONSORS' CONTENT
Burrus rob headshot 300x300

Covid-19 Pandemic: Implications For Managers And Human Resources

Robert Burrus - Cameron School of Business - UNC-Wilmington
Dallas headshot 300x300

Where Transferable Value Comes From

Dallas Romanowski - Cornerstone Business Advisors
Michaelhiggins 41019104338

You’ve Lost A Loved One - What Now?

Michael Higgins - Dignity Memorial

Trending News

Asheville Brewery To Open Taproom In Wilmington

Jessica Maurer - Jul 9, 2020

Analysts Say Successful IPO Could Bring Many Benefits To NCino

Jenny Callison - Jul 10, 2020

Opinion: The $2B Investment Decision

Rob Kaiser - Jul 10, 2020

Partnership, $50K Investment Boost Tech Effort To Promote Black-owned Businesses

Cece Nunn - Jul 9, 2020

Court Ruling Opens Lanes At Wilmington Bowling Alleys

Christina Haley O'Neal - Jul 9, 2020

In The Current Issue

Dosher Memorial Marks 90th Anniversary

Dosher Memorial Hospital in Southport recently commemorated its 90th anniversary. The critical access community hospital opened June 2, 1930...


Industrial Sector Shines In Pender

Industrial commercial real estate gained more attention over the past few months as a sector that’s still doing well, despite an economic do...


The Financing Issues Driving NHRMC Talk

While stakeholders and the public in New Hanover County may differ on the best path toward a sustainable future for New Hanover Regional Med...

Book On Business

The 2020 WilmingtonBiz: Book on Business is an annual publication showcasing the Wilmington region as a center of business.

Order Your Copy Today!


Galleries

Videos

2020 Leadership Accelerator: Virtual Workshops for Real Leaders
2019 Health Care Heroes
August 26, 2019 Power Breakfast: A Healthy Sale?
2019 WilmingtonBiz Expo Keynote Lunch - CEO, nCino, Pierre Naude`