CFPUA Approves $12.8M Construction Contract For U.S. 421 Project

By Christina Haley O'Neal, posted Jan 10, 2018
A nearly $12.8 million construction contract has been approved for the planned U.S. 421 water and sewer utility project that is expected to make available land along the industrial corridor more marketable for business.

During its meeting Wednesday morning, the Cape Fear Public Utility Authority (CFPUA) Board approved awarding the construction contract to T.A. Loving Company, a Goldsboro-based construction firm, according to officials with CFPUA.

The project will bring water and sewer facilities to the industrial corridor along U.S. 421 to the Pender County line. The county and utility authority previously partnered on the planning and design of the project, according to documents in the CFPUA agenda. It's a project that has been in the works over the past three years.

County and regional economic development leaders have said the project is critical to further development of the industrial corridor along U.S. 421, and is the key to making those sites shovel-ready to entice companies. According to CFPUA documents about the project, there is nearly 1,000 acres of developable land available for future industries in the project area.

In the Garner Report – an economic development target analysis report for the city and county done by consulting firm Garner Economics in 2014 – recommended extending water and sewer infrastructure to develop more industrial sites that can be marketed for potential users.

“It’s an exciting project for the authority as well as New Hanover County. And bringing water and sewer services to that corridor is a good development tool to attract businesses and industries to that area,” Carel Vandermeyden, director of engineering for Cape Fear Public Utility Authority, said Wednesday.

Water infrastructure for the project includes bringing 35,000 feet of water main, multiple railroad and N.C. Department of Transportation roadway crossings and fire hydrants to the corridor, as well as 37,000 feet of sewer force main and three pump stations.

It also includes bringing lines under the Northeast Cape Fear River and Fishing Creek near the Pender County line, according to documents.

Funding for the project is coming from the CFPUA's Capital Improvement Program. A portion of funds is also coming from the county, which will fund about $1.6 million over the next three years, beginning in the 2017-18 fiscal year. 

The project is slated to be complete by late 2019. Vandermeyden said the utility expects to have boots on the ground by mid-March. The project overall involves about 18 months of construction, followed by testing, which could take up to 60 days, he said.
Ico insights

INSIGHTS

SPONSORS' CONTENT
Hardyheadshot

Start Your Doctor of Nursing Practice Degree to Get Ahead of the Curve

Charles Hardy - UNCW College of Health and Human Services
Img 0801

The 3 Most Important Questions Before You Retire

Brett Tushingham - Tushingham Wealth Strategies
Img 1576c1

Is Diversification Oversold?

Eddie Nowell - South Atlantic Capital Management Group

Trending News

Wheelz Pizza Aims To Revolutionize Pizza Delivery

Jessica Maurer - May 22, 2019

Cameron Apartment Project Rezoning Request To Come Before Planning Board

Jenny Callison - May 23, 2019

JuSea To Offer Healthy Options On Carolina Beach Boardwalk

Jessica Maurer - May 22, 2019

New Tenants Announced For Leland Retail Center

Cece Nunn - May 23, 2019

Home Sales In April Slumped 12% In Wilmington Area; Decline Blamed On Inventory

Cece Nunn - May 22, 2019

In The Current Issue

Preparing Homes For Hurricane Season

Hurricane season begins June 1, and with it comes the need for residents to prepare themselves and their homes as much as possible for poten...


Trattoria On Market St. Savors Popularity

The eggplant Parmesan is so popular at Rosalie’s Trattoria, the restaurant can’t keep the vegetable in stock, said owner Al Cervini....


Info Junkie: Jim R. Roberts

Info Junkie Jim R. Roberts, Founder of Network for Entrepreneurs in Wilmington (NEW) and Wilmington Angels for Local Entrepreneurs (WALE), o...

Book On Business

The 2019 WilmingtonBiz: Book on Business is an annual publication showcasing the Wilmington region as a center of business.

Order Your Copy Today!


Galleries

Videos

2019 WilmingtonBiz Expo Keynote Lunch - CEO, nCino, Pierre Naude`
Transporting the Future - Power Breakfast 3.12.2019
Health Care Heroes 2018